I’ll Say It: Agile Doesn’t Fit Contract Development at Japanese SIers

Japan Information

This might sound like old news, but I think some things are worth saying plainly: agile development is not a good fit for contract development at Japanese SIers. Here’s why I think that.

First, some background. I work in a department at a Japanese systems integrator, or SIer, that primarily handles AI projects. My work ranges from data analysis and proofs of concept (PoCs) for building models to developing systems for running those models. AI projects often don’t lend themselves to a waterfall approach, so we end up doing something that resembles agile development.

The reason is simple: when we sign a contract for an AI project, it’s impossible to define all the requirements for the system upfront. Defining those requirements takes substantial knowledge of AI and data science, as well as knowledge of the customer’s business. On top of that, we don’t know how well the AI will perform or how it will behave until we’ve tested it in a PoC.

Nobody on either the customer’s side or the vendor’s side has all that information from the start. So instead of following a neat sequence of requirements, design, implementation, and testing, we run several smaller projects. Along the way, we gather information and decide whether to continue or stop, while gradually analyzing the business process, preparing data, developing the model, and building the system to run it, often in parallel. Otherwise, there are too many unknowns to sign a contract in the first place.

That naturally leads us toward something like agile, or more specifically Scrum: dividing the work into sprints and managing requests in a backlog.

My conclusion is that this can work when a company develops a product in-house. But when a vendor is working under a contract and taking direction from a customer, I don’t think it’s workable. At the same time, AI projects can’t be run as straightforward waterfall projects either. We end up with a hybrid, but I think we need to establish a way of working that is neither waterfall nor agile.

By contract development, I mean projects in which a customer provides requirements to a vendor. I’m not talking about an SIer developing its own software products or internal systems. In fact, I think agile is often well suited to those projects, where the decision-maker or product owner is inside the company. I should also admit that my experience with both waterfall and agile is limited, and my knowledge of either is far from complete.

Communication Takes Too Much Time

I’ll start with what I think is the most important issue. When an SIer tries to work in an agile way with a customer and engineers from partner companies, communication costs too much. Or, more accurately, communication can stop working altogether.

If you’re planning to commission or take on an agile project, this is the first thing I’d ask you to think about.

Agile development requires frequent, detailed, real-time communication. The more closely you try to follow Scrum, the more often people have to meet. In particular, the Scrum Master and the product owner need to communicate frequently.

One option is to make the vendor’s project manager or salesperson the product owner, but I don’t think that is likely to succeed. The reason is that they can’t make the final decision in a meeting with the Scrum Master. A salesperson acting as product owner, for example, still has to check with the customer afterward. That takes time, and the customer may reject or overturn the decision. Every time that happens, development stops.

The product owner needs to be someone at the customer’s company who can actually make the final decisions, not just someone assigned to the project.

Then there are the daily Scrums, sprint planning sessions, and sprint reviews. When as many stakeholders as possible are expected to attend, the cost of meetings, measured in hours multiplied by the number of participants, becomes enormous.

On one project I worked on, we used two-week sprints. Everyone from the customer and vendor sides met once a week for a status meeting that also served as sprint planning and review. The customer’s Scrum Master and the vendor’s project manager and project lead met twice a week. The vendor’s project manager, project lead, and working members met another two times a week. Even that wasn’t enough: meetings often ran long, and we ended up working overtime.

I was on the project as both a data scientist and an engineer. Every week, I spent more than a full day preparing materials for the status meeting, which itself took half a day. Afterward, I spent another half day revising the materials and writing the minutes. In the remaining time, I wrote scripts to analyze and process data, trained models, and produced results for the next set of meeting materials. I was doing all this while juggling other projects, and the growing overtime turned it into something of a death march.

It went on for almost two years. I never want to work on a project like that again. Eventually, the customer’s product owner and the vendor’s project manager, who was acting as Scrum Master, wore down, and the project ended before completion. People from the customer, vendor, and partner companies kept leaving; others moved off the project even if they stayed at their companies. In the end, there was money, but nobody left to do the work, or at least nobody who wanted to.

Decisions made in meetings between companies can have legal consequences. That means preparing materials and keeping at least a basic record of what was discussed. There’s a mental cost to that which you don’t face in the same way inside your own company. Explaining something to a customer who doesn’t share the assumptions of your industry can also take much more effort than explaining it to a colleague.

It’s Hard to Give Everyone a Shared Sense of Purpose

You might say this is obvious, but applying Scrum practices to these projects is a stretch: a few weeks per sprint, daily Scrums, and a backlog managed with the customer. Even before we get to the mechanics, the whole mindset feels like a mismatch.

When I joined the company in 2020, my mentor was an advocate of Scrum, so I was made to study it. My mentor worked on packaged software developed in-house, and agile did work for that product. But when I later worked on development projects with customers, I found it much harder to apply what I had learned.

This is partly a matter of attitude, but the mindset Scrum seems to assume is so ambitious that nobody can keep up. For the customer, the system may be just one of many projects. Perhaps someone inherited a project championed by a department head who left last year and doesn’t see the need for it. Or perhaps a business team ordered a system to improve efficiency but is too busy with day-to-day work to give it much thought. Not every customer is personally invested in the project.

I don’t think it’s possible to give everyone on the development side the same sense of purpose either. People join projects for different reasons, and as employees, “my boss told me to” is a perfectly valid one. What matters most to them might be their baseball team’s next game, their child’s grades ahead of high school entrance exams, whether they win tickets to their favorite K-pop group’s tour, or whether that unexpectedly good anime they started watching this season will get a second season. The project’s success comes second or third.

I have worked on my company’s own products, so I understand how people can become personally invested in something they build themselves. But I think it’s unhealthy to expect that kind of Scrum-style commitment to one of several projects for a customer you may only work with for the duration of that contract. SIer projects also bring together people from different companies, sometimes including subcontractors and further tiers of subcontractors. Across company boundaries, I think it’s impossible to give everyone the same sense of purpose.

Too Much Knowledge Ends Up in One Person’s Head

This is more about Scrum than agile in general, but there is an emphasis on moving forward before documentation is fully developed. In projects between companies, there are still documents needed for contractual purposes, so there may not be much that can be eliminated. Meanwhile, requirements and design documents can become inadequate, or simply fail to keep up with changes.

That makes it easy for important information to exist only in the heads of the people doing the work. In an AI project, without documentation, the results of analyzing individual database tables, the approach to preparing and processing data, the work actually performed, and the model-building process can all become things only the person responsible understands.

Then you reach the point where the project can’t move forward without that person.

At an SIer, assignments are fluid, and people are not necessarily dedicated to one project. If a project pauses for two months because of contractual arrangements, for example, someone may be assigned elsewhere and remain unavailable until that other project ends. That sort of thing happens all the time, and handovers aren’t always given much thought.

Partner companies change, and engineers brought in on temporary assignments rotate out. This is an industry where people move around a lot anyway, including when they change jobs.

Once you reach the point where only one person knows how something works and that person is gone, the project is stuck. I’ve seen work effectively lost and projects reset to the beginning after someone left, more than once.

In contract development at an SIer, tasks need to be in a state where someone else can pick them up, regardless of when they are assigned. Ideally, differences in team members’ skill levels should not bring the work to a halt either. That requires managing information through documentation. But I find that difficult to do in agile development: once you make documentation sufficiently comprehensive, the process starts to resemble waterfall, and you lose the benefits of agile.

It Becomes Unclear What the Deliverable Is

I think a quasi-mandate contract may be a more practical solution than a contract for a completed deliverable. In this context, a quasi-mandate is an arrangement centered on carrying out the agreed work rather than promising a specific completed product. Once an agile project starts, it can be hard to say exactly what the customer is receiving in return for the payment.

That is especially true at the start of an AI project. Until you have worked with the data, you often don’t know what is possible. At the PoC stage, you don’t know whether the model will ever be put into operation, let alone how it would be operated. There may be a fairly low chance of getting as far as developing an operational system at all.

So the project can become something vague: examine the data, train a model for the time being, and check its accuracy as a PoC. As the work goes on, it becomes harder and harder to say what the project will actually produce.

You can make a report the deliverable. Another way around the problem is to use a quasi-mandate contract and treat the work of running the sprints as the project’s practical outcome.

But if the project’s purpose is unclear, its direction can keep shifting and the work may never end. The estimated hours are quickly used up, leaving a choice between ending the project with little to show for it or continuing far beyond the estimate and taking a loss.

This is not only a problem for the vendor. In a waterfall project, if the customer can define the purpose and deliverables at the beginning, they can spend the rest of the project checking whether it is proceeding according to plan. With agile under a quasi-mandate contract, the product owner has to keep managing the purpose, problems, and expected outcomes every sprint, or in practice every week. That burden never really ends.

Honestly, you may not even know when you can release anything. And with agile, there is a sense that the real work begins after release, so the burden on the customer never goes away.

You will inevitably face the question: can everyone sustain the budget, the time, and, above all, the motivation over the long term?

In an AI project, it’s impossible to define the exact direction, the value the AI will provide, and the detailed specifications of the operational system from the outset. In the early stages, breaking the work into short projects and proceeding in an agile-like way is unavoidable. Otherwise, the vendor can’t even sign a contract.

But uncertainty shouldn’t be an excuse to leave everything vague. I think it’s important to define the project’s purpose clearly, even if it may need to change later, and to make firm decisions wherever you can.

Perhaps, if you do that well, you can carry the project all the way through using agile. I don’t think you can, but perhaps.

Not having to decide everything at the start also means having to do your best at every decision point that follows. Changing course may be easier than in waterfall, but one mistake in a day-to-day decision can eventually derail the project. There is a constant tension in having to make timely decisions while the project keeps moving.

If someone is going on vacation and can’t do much that week, or is too busy with regular work at the end of a reporting period to spend time in meetings, an internal team might be able to cover for them. When the team is made up of people from several companies, I think there’s a much greater chance that things will fall apart or that people will end up working under exploitative conditions.

Where Do We Go From Here?

I’ve argued that neither waterfall nor agile is a good fit for AI projects, but I don’t know what we should do instead.

A hybrid approach may be the best option available for now, as many people suggest. But I suspect that the extremely poor success rate of AI projects has something to do with how we run them, not just technical problems. I think we need a completely different approach. I just don’t know what it is yet.

For now, I need to keep learning. If I come across something that looks promising, I’ll write about it here.

This article was translated and edited for English-speaking readers from my original Japanese article, published on February 23, 2025.

Until next time.